50 kW unit
Engineering office: BIO4GAS
Start-up: April 2016
MIRO components:
TRANSFER |
AT 34 pump (wash water and manure transfer from the waiting area to the temporary manure storage) |
TEMPORARY MANURE STORAGE |
GTWSB 2040 mixer on stainless steel post |
DIGESTER |
GTWSB 1040 mixer (7.5 kW) |